Structure work (March 2011)
Roofing (May 2011)
This is the picture of the construction progress for our
home. As I said before my husband and I buy this house since there is no
construction was started. Most of our weekends my husband will ask me to follow
him looking for the progress. So if we saw any progress at the site, we will
take the picture to remind how long the structure will be constructing at the
time. After we started to pay the bank interest, our visit to the site became
frequently especially when we get a new charge interest. Basically after end an
office hour, we will straight away go to see the progress. We hope so the
project will finished right before I delivered our little baby but our dream is
just a dream because until the end of my confinement day we still didn’t get
any news from the developer about key collection.
Septic tank installation (Jan 2012)
Painting (March 2012)
Plaster ceiling (March 2012)
drainage base (Mac 2012)
Drainage (May 2012)
Car porch (June 2012)
My husband always asks me for the opinion how long this
project will be finished as I am a civil degree holder and have an experience
as an engineer at the site even it just for 2 months only..hehe. Actually I
can’t give the actual finish work time because in my point of view it will
finish about one year but because this is Kuantan so my expectation is about 2
years or to be exact will finish at December 2012. While according to my
husband calculation the project will be finished maybe at June 2012. And YES I
was right. The project was finished in December 2012 but after that we have to
wait for the application of the Certificate of Fitness (CF) almost 5 months.
Oooh Allah...what a torture have to wait and wait again for another time.
After my confinement date, we decide to send our baby to the
nearer nursery because we think we will move on soon to our new house by
looking at the house progress. Actually the house is almost done on October
2012 so we think by December 2012 we can move on from my in law house about less
than 2 months. But until now May 2013 we still stay with my husband’s family
because there is a lot of work to do before we move on that I have been writing
in this blog before this...huhu. Is there any possibility to move on before
fasting? It’s almost 2 months from now you know but a lot this we did not yet do.
So 3 days from yesterday they did the wiring work but to assemble the fan and
lamp have to wait for my brother because we have to pay double for wiring work
if we want to hire someone. So for double saving we have to wait and wait
again..haha. But by the way not just waiting we will do the painting job after
this. Aaaah what a tired months but anyway can’t hardly wait for the last
result..haha.
2 weeks before delivered
Pavement on my confinement (Sept 2012)